US 15 – (Contract 1)
- Reconstruct US 15 between the Slate
Hill Road Interchange and Gettysburg Road with new asphalt pavement.
- Construct a new interchange at US 15
and Lower Allen Drive (formerly Zimmerman Drive).
- Replace the bridge over Lower Allen
Drive.
- Extend the box culvert at Cedar Run.
- Construct two new concrete retaining
walls at the Lower Allen Drive interchange.
- Construct three new sound barriers
at and south of the Lower Allen Drive interchange.
US 15 – (Contract 2)
PA 581 – (Contract 1)
-
Widen Route 581
Eastbound to provide an auxiliary lane between the US 15 and
Interstate 83 interchanges.
-
Widen the 17 span
viaduct carrying PA 581.
-
Construct one new
concrete retaining wall.
PA 581 – (Contract 2)
-
Construct
acceleration/deceleration lanes and shoulders west of the 18th
Street Overpass (Viaduct) through the US 15/PA 581 interchange.
-
Construct two new
concrete retaining walls.
-
Construct two new sound
barriers.
-
Extend one box culvert.
Reconstructing Side
Roads – (Contract 1)
Reconstructing Side
Roads – (Contract 2)
-
Hummel Avenue
-
Gettysburg Road
-
Simpson Ferry Road
Various Improvements –
(Contract 1 & 2)
-
Add a left turn lane and
temporary ramp from US 15 Northbound to PA 581 WB, and close the
existing ramp from US 15 NB to PA 581 WB (Contract 1).
-
Construct permanent ramp
from US 15 Northbound to PA 581 Westbound (Contract 2).
-
Construct one new box
culvert on the ramp from Zimmerman Drive to Gettysburg Road.
-
Install new storm water
drainage facilities.
-
Complete numerous
utility relocations.
-
Install new guiderail
and concrete barrier.
-
Install new traffic
signing.
-
Install new traffic
signals.
|