Please note that this an anticipated
schedule of construction activities and that this schedule may be
modified as construction progresses.
2008 Construction
US 15 – From Slate Hill Road Interchange
to Gettysburg Road
-
Perform temporary widening along US 15
Northbound and Southbound for traffic control.
-
Construct ramps for new interchange at
Lower Allen Drive (formerly Zimmerman Drive).
-
Construct retaining wall along ramp from
Lower Allen Drive to US 15 Southbound.
-
Construct retaining wall along ramp from
Lower Allen Drive to US 15 Northbound.
-
Construct sound barrier along US 15
Southbound.
-
Construct sound barrier along US 15
Northbound.
-
Construct permanent outside shoulder and
travel lane of US 15 Northbound and Southbound.
-
Construct left-turn lane and temporary
ramp from US 15 Northbound to PA 581 Westbound.
-
Close existing loop ramp from US 15
Northbound to PA 581 Westbound.
PA 581 – Viaduct Bridge over Hummel
Avenue, 22nd Street, and Norfolk Southern Railroad
-
Widen Eastbound side of viaduct bridge
to accommodate a third lane.
-
Widen existing box culvert over Cedar
Run.
-
Install storm water management
facilities along PA 581.
2009 Construction
US 15 – From Slate Hill Road Interchange
to Gettysburg Road
-
Demolish existing US 15 bridge over
Lower Allen Drive (formerly Zimmerman Drive).
-
Construct new US 15 bridge over Lower
Allen Drive (formerly Zimmerman Drive).
-
Construct permanent passing lane and
median shoulder of US 15 Northbound and Southbound.
PA 581 – Viaduct Bridge over Hummel
Avenue, 22nd Street, and Norfolk Southern Railroad
2010 Construction
US 15 – From Slate Hill Road Interchange
to Gettysburg Road
|