2010 Construction
US 15 – From Lower Allen Drive Interchange to Camp Hill Mall (Harvard
Ave.)
-
Reconstruct permanent US 15 Southbound lanes and median
from Lower Allen Drive interchange through the area of
the Camp Hill Mall.
-
Finish construction of the center portion of US 15
bridge over PA 581 (Bridge 1).
-
Reconstruct/widen the Northbound lanes of US 15 bridge
over PA 581 (Bridge 1).
-
Reconstruct/widen the Southbound lanes of US 15 bridge
over Norfolk Southern Railroad (Bridge 2).
-
Begin to reconstruct/widen the Northbound lanes of US 15
bridge over Norfolk Southern Railroad (Bridge 2).
-
Reconstruct/widen the Southbound lanes of US 15 over
Gettysburg Road (Bridge 3).
-
Begin to reconstruct/widen the Northbound lanes at US 15
over Gettysburg Road (Bridge 3).
-
Permanently remove existing ramp access to/from US 15
to/from Gettysburg Road.
-
Begin to reconstruct/widen US 15 Northbound lanes from
Lower Allen Drive through the area of the Camp Hill
Mall.
PA 581 – West of SR 15/581 Intersection to Viaduct Bridge over Hummel
Avenue
-
Construct Ground Mounted Sound Barrier Wall NSA6 along
Ramp A and PA 581 Westbound.
-
Construct Ground Mounted Sound Barrier Wall NSA4 along
Ramp H and PA 581 Westbound.
-
Construct collector/distributer road for PA 581
Westbound and Eastbound in the area of US 15/PA581
interchange.
Ramps
-
US 15/PA 581 Interchange - construct temporary Ramp A.
-
US 15/PA 581 Interchange - construct permanent Ramps A,
C, G, H,& F.
-
Install a permanent traffic signal at Ramp H spur and SR
11/15.
-
Complete PA 581 Eastbound acceleration lane from Ramp F.
-
Construct PA 581 Westbound deceleration lane Ramp A.
Gettysburg Road (SR 2014)
-
Construct Gettysburg Road Box Culvert extension for
Cedar Run Tributary.
-
Install drainage.
-
Overlay Gettysburg Road/Hummel Ave.
-
Install permanent traffic signal at Gettysburg Road and
Linda Lane.
2011 Construction
US 15 – From Lower Allen Drive Interchange to Camp Hill Mall (Harvard
Ave.)
-
Complete the reconstruction/widening of the Northbound
lanes of US 15 bridge over Norfolk Southern Railroad
(Bridge 2).
-
Complete the reconstruction/widening of the Northbound
lanes of US 15 over Gettysburg Road (Bridge 3).
-
Complete US 15 Northbound reconstruction with final
wearing surface.
-
Install guiderail, signing, lighting. Install permanent
median barrier.
-
Install permanent pavement markings for US 15 and PA
581.
Gettysburg Road (SR 2014)
|