US 15/PA 581 Improvement Project - Monthly Project Update

August 2010

The following projected work activities are derived from the contractor's anticipated schedule, and are subject to change.

US 15

  • US 15 Northbound between Lower Allen Drive Interchange and Camp Hill Mall - US 15 Northbound at the south end of the project has been shifted slightly east to allow the contractor reconstruct a portion of Bridge 3 (US 15 over Gettysburg Road.).  Just north of Bridge 2 (US 15 over Norfolk Southern Railroad), US 15 NB traffic is shifted west into the passing lane and median of US 15 SB for the construction of the new US 15 Northbound bridge over PA 581, before returning to the normal US 15 NB alignment just south of Harvard Avenue.  During this phase (anticipated to remain in effect through October 2010), Dickenson and Columbia Avenues will be closed at US 15, preventing all turning movements at these intersections.  Two lanes of unrestricted traffic are being maintained in both directions of US 15 during daytime hours.  From 9:00 PM to 6:00 AM, single-lane traffic restrictions are permissible in both directions on PA 581 and are possible for construction activities.

  • US 15 Southbound between Camp Hill Mall and Lower Allen Drive Interchange -  US 15 SB traffic has been shifted west and merges with Ramp C (PA 581 WB to US 15 SB) traffic just north of Bridge 1 (US 15 over Pa 581) at a newly installed temporary traffic signal.  Both Ramp C (PA 581 WB to US 15 SB) traffic and US 15 SB traffic travel across the newly constructed portion of Bridge 1 (US 15 over PA 581) and merges with Ramp D (PA 581 EB to US 15 SB) traffic at a recently installed temporary traffic signal just north of Bridge 2 (US 15 over Norfolk Southern RR).  US 15 SB, Ramp C, and Ramp D traffic then continue across the newly constructed portions of Bridge 2 (US 15 over Norfolk Southern RR) and Bridge 3 (US 15 over Gettysburg Road) then return to the normal US 15 SB alignment. This phase is anticipated to remain in effect throughout the summer months. Two lanes of unrestricted traffic are being maintained in both directions of US 15 during daytime hours.  From 9:00 PM to 6:00 AM, single-lane traffic restrictions are permissible in both directions on PA 581 and are possible for construction activities.

  • Continue construction of Northbound portion of Bridge 1 (US 15 over PA 581).

  • Continue construction of remaining portion of new SB structure of Bridge 2 (US 15 over the Norfolk Southern RR).

  • Continue construction of a portion of the new SB structure of Bridge 3 (US 15 over Gettysburg Road).    

  • Place bituminous pavement for new US 15 SB lanes.

  • Continue installing highway lighting.

  • Continue installing drainage pipe and inlets.

  • Continue erecting overhead sign structures.

 

PA 581

  • PA 581 from Viaduct Bridge over 18th Street to US 15 / PA 581 Interchange - PA 581 Eastbound and Westbound traffic from the Viaduct Bridge over 18th Street continuing west through the US 15/PA 581 interchange has been shifted slightly to the south to permit construction/widening for declaration/acceleration lane along PA 581 WB.  Two lanes of unrestricted traffic are being maintained in both directions of PA 581 during daytime hours.  From 9:00 PM to 6:00 AM, single-lane traffic restrictions are permissible in both directions on PA 581 and are possible for construction activities.

  • Continue construction of Ground Mounted Sound Barrier Wall NSA-6 (S-26598) along PA 581 WB and new Ramp A.

  • Continue construction of Ground Mounted Sound Barrier Wall NSA-6 (S-26606) along PA 581 WB and new Ramp H.

  • Install drainage pipe and inlets.

  • Continue erecting overhead sign structures.

  • Continue installing highway lighting.

US 15 / PA 581 Interchange Ramps

  • All US 15/PA 581 ramp movements are being maintained in permanent or temporary configurations at all times with the exception of the Ramp G detour as noted below.

  • Ramp G (PA 581 EB to US 15 NB) Detour – Ramp G (PA 581 EB to US 15 NB) is currently closed and traffic is being detoured to the Lower Allen Drive interchange via Ramp D (PA 581 EB to US 15 SB).  This detour is anticipated to remain in effect through October 2010.  Signing will be in place to direct traffic along the detour route. Visit http://www.penndot8.com/projects/0015-006/Images/ramp_g_detour.swf for an animated detour map.

  • Continue reconstruction of permanent Ramp F (US 15 NB to PA 581 EB); Ramp G (PA 581 EB to US 15 NB).

  • Continue construction of PA 581 Eastbound and Westbound collector distributer roads.

  • Continue installing highway lighting.

Lower Allen Drive (Formerly Zimmerman Drive)

  • Lower Allen Drive is open to unrestricted traffic in the final configuration.  Short term lane closures are possible to complete miscellaneous work activities.

  • Install pedestrian push buttons on traffic signals.

Gettysburg Road

  • Long-term single lane closures are in effect for WB and EB Gettysburg Road traffic in the area of the US 15 Bridge to protect the work zone and facilitate the US 15 Bridge work. 

  • The existing ramps to and from US 15 at Gettysburg Road have been permanently closed.  Local traffic entering and exiting US 15 must now do so at the new Lower Allen Drive Interchange just south of Gettysburg Road

  • Gettysburg Road Detour Gettysburg Road between the Bon-Ton and Simpson Ferry Road, has been detoured to permit ramp reconstruction.  This detour is anticipated to remain in effect through October 2010.  Visit http://www.penndot8.com/projects/0015-006/Images/2027_detour.swf for an animated detour map. 

  • Install traffic signal equipment at Gettysburg Road/Simpson Ferry Road intersection.

Linda Lane

  • Traffic is currently running unrestricted in the existing lanes of traffic.

  • The cul-de-sac is being used to access the SR15 Bridge over Norfolk Southern RR.