I-81 Exit 44 Improvement Project - Tentative Schedule
Project Start - April 2009
Project Completion - Late 2010

I-81 Bridges over Route 465 (Please Refer to Special Features for Staging)
Stage 1 - Summer 2009
Stages 2 thru 4 - Fall 2009 to Spring 2010
Stage 5 - Spring 2010
Stage 6 - 2010
Final Condition - Fall 2010

Route 465 (Allen Road)
Stage 1 - Temporary Widening on West Side, South of I-81 - Summer 2009
Stage 2 - Construct NB side of Route 465, South of I-81 - Summer 2009 to Spring 2010
Stage 3 - Construct SB side of Route 465, South of I-81 - Spring and Summer 2010
Stage 4 - Temporary Widening on West Side, North of I-81 - Spring 2010
Stages 5 and 6 - Construct Route 465, North of I-81 - 2010

Alexander Spring Road, East of Route 465 - Fall 2009 and Spring 2010

East Commerce Avenue - Spring 2010

US 11 (Ritner Highway) - 2010