Project Start - April 2009
Project Completion - Late 2010
I-81 Bridges over Route 465 (Please Refer to Special Features for Staging)
Stage 1 - Summer 2009
Stages 2 thru 4 - Fall 2009 to Spring 2010
Stage 5 - Spring 2010
Stage 6 - 2010
Final Condition - Fall 2010
Route 465 (Allen Road)
Stage 1 - Temporary Widening on West Side, South of I-81 - Summer 2009
Stage 2 - Construct NB side of Route 465, South of I-81 - Summer 2009 to
Spring 2010
Stage 3 - Construct SB side of Route 465, South of I-81 - Spring
and Summer 2010
Stage 4 - Temporary Widening on West Side, North of I-81 - Spring
2010
Stages 5 and 6 - Construct Route 465, North of I-81 - 2010
Alexander Spring Road, East of Route 465 - Fall
2009 and Spring 2010
East Commerce Avenue - Spring 2010
US 11 (Ritner Highway) - 2010 |