July 2010
I-81 Northbound (NB) and
Southbound (SB)
-
Northbound and southbound traffic is in a
temporary traffic pattern to allow for the construction
of four new ramps for the I-81 Exit 44 Interchange. Two
lanes of unrestricted traffic are maintained on I-81 NB
and SB between 6:00 AM and 7:30 PM, with single lane
closures permitted between the hours of 7:30 PM and 6:00
AM.
-
Demolition of the existing bridge and
abutments is completed and construction of the remainder
of the new bridge structure over Allen Road is
continuing.
-
Southbound traffic exiting to Allen Road (PA
465) is travelling on a partially-completed section of
the new Off-Ramp. Construction of the remainder of the
new ramp is continuing.
-
Northbound traffic exiting to Allen Road (PA
465) is traveling on a partially-completed section of
new Off-Ramp.
-
Vehicular traffic entering southbound I-81
from Allen Road is traveling on a new On-Ramp.
I-81 Bridge over PA 465
(Allen Road)
PA 465 / PA 3023 (Walnut
Bottom Road)
PA 465 (Allen Road) between
Walnut Bottom Road and Alexander Spring Road
-
Northbound and Southbound traffic is traveling
on a newly completed segment of Allen Road, between
Walnut Bottom Road and Alexander Spring Road.
Construction of the west side of Allen Road is nearing
completion.
PA 465 (Allen Road) between
Alexander Spring Road and the I-81 Exit 44 Interchange
-
Southbound traffic is traveling on temporary
pavement and northbound traffic is traveling on the
existing southbound roadway. Construction is continuing
for the new roadway on the east side of Allen Road
between Alexander Spring Road and the existing On-Ramp
from Allen Road to northbound I-81.
-
The new Off-Ramp from northbound I-81 to Allen
Road is open to vehicular traffic. A temporary traffic
signal is in operation at the intersection of the new
Off-Ramp, Allen Road and East Commerce Avenue, and will
remain in operation during construction.
-
Construction is continuing for the new On-Ramp
from southbound Allen Road to northbound I-81.
-
Reconstructed East Commerce Avenue is open to
vehicular traffic.
PA 465 (Allen Road) between
the Exit 44 Interchange and US 11 (Ritner Highway)
-
The new On-Ramp from Allen Road to southbound
I-81 is open to vehicular traffic.
-
Reconstruction along the east and west sides
of Allen Road is continuing. Unrestricted traffic is
maintained between 6:00 AM and 9:00 AM, and between 3:00
PM and 6:00 PM. Single lane closures are permitted
between 9:00 AM and 3:00 PM, and between 6:00 PM and
6:00 AM.
-
Logistics Drive, for a distance of
approximately 500 feet off of Allen Road, is closed for
reconstruction. A
detour is currently in place.
US 11 (Ritner Highway)
-
Vehicular traffic is traveling along the north
side of Ritner Highway. Reconstruction along the south
side of Ritner Highway and near the intersection of
Ritner Highway and Allen Road is continuing.
PA 465 (Allen Road) between US 11 (Ritner Highway) and Newville Road (PA
641)
|